APPROVAL PROCESS

Building Plan & Land Subdivision Approvals

Planning & Building regulations

A booklet of Planning and Building regulation formulated according to the gazette issued in 1986 are available for sale at Finance Division of Urban Development Authority between 8.30 am to 3.00 pm.

Local Authority Monitoring Evaluation

Among the tasks undertaken by Enforcement division supervision and monitoring of Local authorities is a key area regards to Planning Approvals & sub division approvals.

1) Process of Building Planning Approvals and Land Subdivision Approvals handled by the UDA is as follows

Common Process Adopted for Preliminary Planning Clearance

(Development Permits, COC, Subdivision Approvals)

Application Submission to Enforcement division with Processing fee relevant and Obtain File number
Forwarding Application to Director Enforcement
Processing of Application Internally.
Site Inspection by UDA
Submission of inspection Report with Recommendation to Director Enforcement
Issuance of Planning Clearance within a week if there are no any issues Related
If further Queries, file will be forwarded to the Sub Committee
If further Queries, file will be forwarded to the Main Committee
Decisions
Documents Required to Attached with Application for CMC area Clearances, Development Permits, COC, Subdivisions, Ownership Certificate/Deed, Survey Plan, Approvals of the Agencies, Location Map, Consent Letter
Documents Required to Attached with Application for non CMC area Clearances Application form, Survey Plan, Deed, Approvals of the Agencies, Location Map
Total Processing time taken for CMC area Applications: 7 Working Days

Total time taken for Non CMC Area clearances :12 working days.

If further enquires/ Complains: Contact Director Enforcement on: 011 2872616

2) Process of Building Planning Approvals and Land Subdivision Approvals handled by the Local Authority is as follows

Process of Building Planning Approval & Land Sub Division Planning Approval Via respective area Local Authorities

Application Submission to respective local Authorities together with Relevant Documents.
If all relevant documents & regulations are in order, Development Permits will issue by Local Authority
Scrutinizing the application by Director Enforcement, if no complex issues, decisions will take. If further queries available application will be forwarded to Regional Committee.
Local Authority matters forwarded to regional council by the relevant officer & issues of Planning and Building & Regulations
(If further Queries available)
Unsorted Clearance, Permits, COC, and issue of Planning & Building regulations, matters of provincial and district officers of the UDA and other agency matters produced to review of Sub Committee
Submission to review of Sub Committee of Enforcement Division
(If further Queries available)
Submission to review of Main Committee
Decision taken

ගොඩනැගිලි සැලසුම් අනුමැතිය

නාගරික සංවර්ධන අධිකාරියේ නීතිය යටතේ ප්‍රකාශයට පත් කරනු ලැබූ බල ප්‍රදේශ තුල ඉදි කරනු ලබන්නා වූ සියලුම ගොඩනැගිලි සඳහා ගොඩනැගිලි සැලසුම් අනුමැතීන් නිකුත් කිරීම නාගරික සංවර්ධන අධිකාරිය විසින් ඉටු කරනු ලබන්නා වූ සේවාවකි. මේ යටතේ සංචාරක සංවර්ධන අධිකාරිය හරහා ඉදිරිපත් කරනු ලබන සියලූම හෝටල් සංවර්ධනයන්ට අදාලව ගොඩනැගිලි සැලසුම් අනුමත කිරීම් සහ කොළඹ නාගරික බල ප්‍රදේශය තුල ඉදි කිරීමට යෝජිත විශේෂිත අධි උස ගොඩනැගිලි සංවර්ධනයන් සඳහා වන ගොඩනැගිලි සැලසුම් අනුමත කිරීමද මේ යටතේ ලබා දෙනු ලබන සේවාවක් වේ.